|
Compensation
for delay in flat construction |
|
Source:
THE NEW INDIAN EXPRESS, 22-April-2002 |
|
|
|
In
a recent judgment, the Hyderabad District Consumer Disputes Redressal
Forum-II directed the apartment contractors of a flat to pay a buyer
compensation for the delay in handing over the flat to him.
|
|
Sumit
Puri filed a complaint against Y.Rajan and Raviraj Mathur, partner
contractors and builders, and the owner of the land Usha Mathur. He
alleged that they agreed to sell him a semi finished flat in Santosh
Bhavan, admeasuring 900 square feet, together with an undivided share of
29 square yards land, for a total consideration of Rs 6,60,000. A sale
deed was executed dated 11.11.1999 in his favour. The builders promised to
complete the unfinished work and provide all the common amenities, parking
space etc within two months, on 12.11.1999, they executed a promissory
note agreeing to complete the work by 8.2.2000; they also agreed to pay Rs
5,000 per month as damages, in case of any delay. The complainant paid a
total of Rs 6,85,000, which they acknowledged in a letter dated 18.6.2000.
He charged that they collected more money for the extra work but did not
complete it.
|
|
Vexed
with their attitude, Summit Puri demanded that they pay him damages. Then
they promised to complete certain jobs within 10 days from 29.9.2000. He
charges that sufficient car parking space was not provided and also that
the builders had constructed a 4 thick wall, while promising to construct
a 9-thick brick compound wall.
|
|
He
approached the Forum seeking Rs 6,518 towards floor polishing and Rs
50,000 damages at Rs 500 per month for the delay of 10 months, from
18.2.2000 till the date of filing. He also sought Rs 50,000 compensation
for mental agony and inconvenience and a direction to the builders to
complete the work or pay him Rs 60,000, towards its value. He further
demanded payment of Rs 5,000 per month from 8.1.2001 till the completion
of the pending works and costs.
|
|
The
contractors said that he paid Rs 6,60,000, and made an agreement for
completing the remaining works for Rs 2,10,000. But he paid the amount
only by 19.6.2000, the delay in execution of the works was due to this non
payment. They denied their liability to pay Rs 5,000 per month. They said
adequate car parking space had been provided. They denied the promise to
construct a nine inch wall, as it would add weight on the structure. Sumit
Puri said the sale consideration was Rs 4,50,000 for the semi finished
flat and Rs 2,10,000 for completing the work; the builders said it was Rs
6,60,000 for the semi-finished flat. plus an additional Rs 2,10,000 for
completing the work; the builders said it was Rs 6,60,000 for the semi
finished flat, plus an additional Rs 2,10,000 for the extra work. In the
sale deed, the sale consideration is shown as Rs 4,50,000. They said that
to reduce their stamp duty and registration charges, a lesser amount was
mentioned.
|
|
This
case falls to ground under the Evidence Act. Oral evidence, contrary to
the recitals of a written document, can not be admitted. If the sale
consideration was falsely mentioned as Rs 4,50,000 the amount received by
them would also have been falsely stated as Rs 4,50,000. What ever the
actual sale price, they would have definitely received the full amount
before executing the sale deed, or stated the balance payable. It is
unlikely that they would have delivered the flat without receiving full
consideration.
|
|
The
builder's letter dated 18.6.2000 says that they have received Rs 6,50,000,
asking for an additional Rs 60,000 towards miscellaneous work, including
water and electricity and car parking. They asked for Rs 35,000 at that
time, and the balance at the time of taking possession of the flat. They
have not demanded any amount towards sale consideration. The letter also
acknowledges receipt for Rs 35,000. Further, no notice was issued
demanding the balance sale consideration. However, the complainant too did
not pay the full amount till June 2000. Hence the delay in delivery was
from June 2000 till September 2001. The compensation of Rs 5,000 per month
for the delay is not unreasonable and he is entitled to 14 months
compensation, i.e., Rs 70,000.
|
|
The
amount paid towards car parking is also liable to be refunded. Regarding
the compound wall of 9", the builder has justified his stand. Admittedly,
the specifications do not mention the thickness of the compound wall.
Hence, the Forum directed the contractors to pay a compensation of Rs
70,000 and refund him Rs 63, with 12 per cent interest per annum, from
2.1.2001 till the date of filing the complaint, and thereafter with
interest at 18 per cent per annum till payment. He was also awarded costs
of Rs 1000.
|
|
The
judgment was delivered by Y.Venkateswara Rao, president, and M.R.Naik and
Bela Sumanth, both members.
|
|