|
Interlinking
of rivers — II |
|
|
|
By
A. Vaidyanathan
|
|
It
is difficult to believe that the interlinking programme has been worked
out in sufficient detail to qualify for serious examination, leave alone
immediate implementation.
|
|
ENTHUSIASTS
OF interlinking of rivers tend to be dismissive of the concerns over the
environmental and human consequences of the project. They claim that these
fears are vastly exaggerated or argue that they are unavoidable costs of
"development" and that they should not be allowed to hold back
the project. One has to be extraordinarily insensitive not to recognise
the consequences of ignoring these aspects in our water resource planning
in the past. They are reflected in the callous manner in which displaced
persons have been treated, land degradation due to misuse of water,
depletion of groundwater and the growing pollution of water sources. The
experience of the Indira Gandhi Canal is a stark example of the problems
arising in the wake of bringing in vast amounts of water without adequate
understanding of and concern for its impact on the fragile desert ecology.
|
|
There
are also good reasons to be sceptical about the state of preparation for
the interlinking projects. Anyone familiar with the planning of projects
such as Bhakra Nangal and Sardar Sarovar knows that the detailed
investigations and site surveys preparatory to the design and the analyses
and studies needed for the actual design take many years of intensive
effort and expense by a large body of experts in diverse fields. A mega
project of such complexity as interlinking of rivers calls for preparatory
work of far, far greater dimensions. Moreover, the quality of preparatory
investigations and surveys for many, if not most, of the irrigation and
water resource projects leave much to be desired. Inadequate
investigations, changes in scope and design, huge cost escalations and
inordinate delays in completing projects are all-too-familiar features of
irrigation planning in the recent decades.
|
|
Under
these circumstances, it is difficult to believe that the interlinking
programme has been worked out in sufficient detail to qualify for serious
examination, leave alone immediate implementation. The best way to counter
this scepticism is to make all the studies, analyses and reports available
for public scrutiny.
|
|
There
is little authenticated information on the likely cost of the programme
and its various component projects. Figures as high as Rs. 5,600 billion
are mentioned but no details are available. This is about 50 times the
total allocation for the ongoing water resource development projects in
the Tenth Plan.
|
|
In
a situation of severe resource scarcity, the question of the relative
priorities to be accorded to the improvement of existing facilities and
the expeditious completion of viable projects on hand as against mega
projects based on questionable premises is particularly relevant. This
issue ought to be debated seriously. Questions about the sources of funds
for interlinking tend to be dismissed cavalierly. The notion that private
sources can be attracted is the height of naivete and wishful thinking. A
Government already saddled with huge public debt, and whose precarious
fiscal situation continues to deteriorate rapidly, can hardly expect the
financial institutions to fork out such large sums for a programme, the
content and economic viability of which have not been assessed.
|
|
There
are also important institutional and legal issues to be sorted out. There
is no provision for any mechanism to deal with matters concerning
inter-basin transfers. The Centre has no legal authority to decide on this
and no State will agree to vest the authority with the Centre. There is
talk of deciding these matters through consultation and consensus among
the States. One can hardly take this seriously, given our experience with
the working of existing laws and procedures for dealing with water
allocation between the States within the same basin. The allocation of
water among riparian States even within a single river basin has so far
been determined by law through negotiated legal agreements and treaties,
and by judicial and quasi-judicial mechanisms such as tribunals. We know
from experience how contentious, prolonged and difficult this process is.
The awards themselves have so far been accepted as binding on all the
States concerned and the Centre. But the implementation of these awards
has given rise to innumerable inter-State conflicts, which the Centre,
despite the powers given to it under the law and its financial clout, has
been unable to prevent or settle. These disputes and conflicts are the
subject of numerous litigations. The courts have been cautious in dealing
with these cases and have instead suggested that they be settled through
mutual discussion, arbitration, Central mediation and other extra-judicial
mechanisms.
|
|
This
caution is both wise and understandable, given the complexity of the
issues involved and the fact that courts have no means to enforce the
judgments and the record of compliance by Governments is at best mixed. No
judgment or award can satisfy all the interested parties. Indeed, of late,
the States are pleading their inability to enforce court judgments on
grounds that they are unfair and likely to cause unmanageable law and
order problems. Instances of Governments condoning blatant violations of
their own rules regarding allocation of uses of water and acquiescing or
even permitting the violation of established rules regarding the rights of
access and use are distressingly widespread.
|
|
These
questions are pertinent and basic to a considered assessment of the
river-linking programme. In the absence of satisfactory answers,
criticisms of the decision to go ahead with the implementation of the
project are reasonable and legitimate. The current discussions in the
media and on public forums hardly focus on these issues, much less help
allay the apprehensions. That would call for a serious, open and informed
debate based on facts and analyses. Regrettably, apart from a few sketch
maps purported to be taken from the Hashim Commission report, very little
information on the specific schemes envisaged, details of their design,
environmental impact, displacement, and likely costs and benefits is
available in the public domain.
|
|
Even
the main report of the Commission, though claimed to be a priced
publication, cannot be obtained from either the Ministry or the
Publications Division. The annexure to the report, in which the details
have reportedly been discussed, are considered secret.
|
|
Time
was when the opinions of the Government's irrigation establishment were
accepted without much question. Times have changed. There is much greater
awareness now that there is more, much more to water resource development
than constructing dams and canals, that the process of scrutiny and
appraisal is at once too narrow, too lax and too secretive, and that there
is now a sizeable body of knowledge and expertise on water resource
management outside the Government. The assessments of the engineering
establishments are no longer taken as beyond challenge. Hardly anyone
takes seriously, much less accepts, the claim that "the National
Perspective Plan (linking rivers) has been drawn up by a scientific and
professional organisation, conceptually and technically upheld by the
Technical Advisory Committee of the Ministry of Water Resources, the
Central Water Commission and the National Commission on Integrated Water
Resources Development Plan... " and that "... the studies have
been ratified by engineers, sociologists and economists". If this is
so, why should the details of these studies and appraisals be a
closely-held secret, instead of being made public to facilitate informed
discussion?
|
|
The
least that Suresh Prabhu, head of the task force on interlinking rivers,
can do is to make all the relevant reports and documents available to the
public and provide an opportunity for various interested "stake
holders" to voice their concerns.
|
|
(Concluded)
|
|